 KPI Name / Definition  | Representation  | Tool  | Maturity Levels  | KPI Calculation  | On Hover  | Remarks  | 
Deployment Frequencymeasures how often code is deployed to production 
  | Line chart 
 
  | Agile Project Management 
 
  | M1: 1 M2: 2-3 M3: 4-5 M4: 6-7 M5: >=8  | It is calculated as No. of deployments done on a environment in a month 
  | Month - <<Count>>  | 
 
  | 
Change Failure Ratemeasures the proportion of builds (changes) that have failed for whatever reason over a given period of time  | Line Graph with single-select filter 
  | Build 
  | M1: >60% M2: 45-60%, M3: 30-45%, M4: 15-30%, M5: <15%  | Total no. of failed Builds/Total number of Builds 
 *If the KPI data is not available for last 5 weeks, the Maturity level will not be shown  | Date Range: <<Percentage>> Total number of Changes: <<Value>> Failed Changes: <<Value>> 
  | 
  | 
Lead time for changesgauges the speed of software delivery by measuring the duration between a code change and its deployment in production. It provides visibility into the efficiency and effectiveness of the development process.  | Line Graph with single-select filter 
  | JIRA Repos  | M1: >3 Months M2: 1-3 Months, M3: <1 Month, M4: < 1 week, M5: < 1 Day  | 
  | Date Range: <<Lead time in Days>> 
  | 
  | 
Mean time to Recover (MTTR)is a metric that measures the average time taken to recover from production incidents. It is calculated based on the production incident tickets raised during a certain period of time.  | Line Graph 
  | JIRA  | M1: >1 Week M2: 1 day - 1 week, M3: 12-24 Hours, M4: 1-12 Hours, M5: < 1 Hour  | 
  | 
  | 
  | 