Issues likely to spill

KPI Name

Overview

Applicability

Scrum-based projects

Definition (info)

Measures the number of work items that are not adequately refined in time for development planning, as per Definition of Ready (DoR) criteria. This includes:

  • Work items in the current sprint that do not meet DoR (Definition of Ready).

  • Work items tagged to the next sprint that lack sufficient refinement (e.g., missing description, acceptance criteria, etc).

Late Refinement Sprint Readiness metric flags backlog items that should be refined by now but aren't, either because they’re already in the current sprint and not meeting the Definition of Ready (DoR), or because they're slated for the next sprint but still lack necessary refinement details.

Calculation Logic

  • LateRefinementRate_CurrentSprint = (Unrefined items in current sprint / Total items in current sprint) * 100

  • LateRefinementRate_NextSprint = (Unrefined items in next sprint / Total items in next sprint) * 100

    Source Tools

    Jira, Azure Board

    Graph type

    Line chart for Current Sprint
    Single stats for Next Sprint

    Filters

    Filter by Issue type

    Hover Format on datapoints

    1. Date

    2. No. of unrefined items : <<Count/Size>>

    3. Total items : <<Count/Size>>

    Columns in Explore overlay

    1. Issue ID

    2. Issue Type

    3. Issue Description

    4. Issue Priority

    5. Size (Story Point/Days)

    6. Issue Status 

    7. Original Estimate

    8. Remaining Estimate

    9. Due Date

    10. Actual Start Date

    11. Dev Completion Date

    12. Actual Completion Date

    13. Delay

    14. Predicted Completion Date

    15. Assignee
      and more…

    Business Logic

    Calculation Logic

    1. Unrefined_CurrentSprint = (Unrefined items in current sprint / Total items in current sprint) * 100

    2. Unrefined_NextSprint = (Unrefined items in next sprint / Total items in next sprint) * 100

    Scope of detection

    1. Current Sprint Work Items
      Assigned to the current active sprint but do not meet DoR (status, fields).

    2. Next Sprint Work Items
      Tagged for the next sprint but lack key refinement attributes such as Description, Acceptance criteria,etc

    Configuration (Field Mapping)

    Processor Fields

    1. Refinement criteria

      1. Custom field to consider for a refined workitem
        Provide field name to identify a refined workitem, Example : customfield_13999

      2. Custom field value min length

      3. Keywords to match (case-insensitive, ALL match)

    Mandatory fields

    1. Issue types to consider

    2. Status/es before DOR

    Refinement Criteria

    Work item is considered refined if it meets all of the following:

    • Status is one of: Refined, Ready for Dev, or equivalent

    • Has a non-empty description or, has specific keywords

    • Includes clearly defined acceptance criteria

    Benefits of KPI

    How does the KPI help?

    1. Detect bottlenecks in sprint execution early

    2. Improve quality of sprint planning

    3. Avoid last minute clarifications and context gaps